Fully loaded labor cost
Include the costs beyond salary.
Example: productive time changes hourly cost
$75,000 salary + $6,000 employer taxes + $10,000 benefits + $9,000 overhead gives $100,000 annual loaded cost. Dividing by 1,600 productive hours gives $62.50 per hour.
Read the result
At 1,400 productive hours, the same annual cost becomes about $71.43 per hour. Use applicable employer costs and distinguish paid hours from productive hours; avoid allocating overhead twice.
How it works
Annual loaded cost = salary + employer taxes + benefits + allocated overhead. Cost per productive hour = annual loaded cost ÷ productive hours. Enter actual applicable costs and avoid counting overhead twice.
These are planning estimates based on your inputs, not promised savings or a forecast of actual results. Amounts use USD.